(solution) Task 1 Question: Review the WBS and Gantt chart you created for
Task 1 Question: Review the WBS and Gantt chart you created for Tasks 3 and 4 in Chapter 5. Propose three to five additional activities that would help you estimate resources and durations. Write a one-page paper describing these new activities.
Task 2 Question: Identify at least five milestones for the Global Treps Project. Write a short paper describing each milestone using the SMART criteria. Discuss how determining the details of these milestones might add activities or tasks to the Gantt chart. Remember that milestones normally have no duration, so you must have the tasks that will lead to completing them.
Task 3 Question: Using the Gantt chart you created for Task 4 in Chapter 5 and the new activities and milestones you proposed in Tasks 1 & 2 above, create a new Gantt chart using Project 2013 or another tool. Estimate the task durations and enter dependencies as appropriate. Remember that your schedule goal for the project is six months. Print the Gantt chart and network diagram, each on one page.
Task 4 Question: Write a short paper summarizing how you would assign people and/or dollars to each activity from Tasks 1, 2, and 3. Include a table or matrix listing how many hours each person would work (or how many dollars you would assign) for each task. These resource assignments should make sense given the duration estimates made in Task 3 above. Remember that duration estimates are not the same as effort estimates because they include elapsed time.
1 Task 1 Question: Review the WBS and Gantt chart you created for Tasks 3 and 4 in
Chapter 5. Propose three to five additional activities that would help you estimate
resources and durations. Write a one-page paper describing these new activities.
Task 2 Question: Identify at least five milestones for the Global Treps Project. Write a
short paper describing each milestone using the SMART criteria. Discuss how
determining the details of these milestones might add activities or tasks to the Gantt
chart. Remember that milestones normally have no duration, so you must have the
tasks that will lead to completing them.
Task 3 Question: Using the Gantt chart you created for Task 4 in Chapter 5 and the
new activities and milestones you proposed in Tasks 1 & 2 above, create a new Gantt
chart using Project 2013 or another tool. Estimate the task durations and enter
dependencies as appropriate. Remember that your schedule goal for the project is six
months. Print the Gantt chart and network diagram, each on one page.
Task 4 Question: Write a short paper summarizing how you would assign people
and/or dollars to each activity from Tasks 1, 2, and 3. Include a table or matrix listing
how many hours each person would work (or how many dollars you would assign) for
each task. These resource assignments should make sense given the duration estimates
made in Task 3 above. Remember that duration estimates are not the same as effort
estimates because they include elapsed time. 2 Task 3 Answer: Work Breakdown Structure for Global Treps
Prepared by: Group 3 Date:10/8/16 1.0 Initiating
1.1 Present project options
1.2 Select project
1.3 Gather requirements
1.4 Develop project charter
2.0 Planning
2.1 Refine Requirements
2.1.1 Combine requirements
2.1.2 Prioritize requirements
2.2 Develop scope statement
2.3 Develop WBS
2.4 Acquire and Deploy 3 laptops for
team members abroad
3.0 Executing
3.1 Website
3.1.1 Concept
3.1.1.1 Define requirements
3.1.1.2 Define functionality
3.1.1.3 Define risk & risk management plan
3.1.1.4 Develop project plan
3.1.1.5 Brief Bobby
3.1.2 Website design
3.1.2.1 Consult with professional web developer
3.1.3 Website development
3.1.3.1 Code website and databases
3.1.3.2 Solicit feedback from consultant
3.1.3.3 Solicit feedback from users
3.1.3.4 Make revisions as needed
3.1.4 Rollout
3.1.4.1 Secure hosting medium
3.1.4.2 Deploy website
3.1.5 Support
3.1.5.1 Fix bugs as necessary
3.2 Events
3.2.1 Plan
3 3.2.1.1 Locate venues for events
3.2.1.2 Secure catering
3.2.1.3 Arrange props, seating, sound, etc.
3.2.1.4 Develop communication plan with vendors
3.2.1.5 Arrange for translator
3.2.2 Coordinate
3.2.2.1 Communicate with vendors and personnel
3.2.2.1 Address issues as needed
3.2.3 Execute
3.2.3.1 Host the event
3.2.3.2 Address issues as needed
3.3 Business plan
3.3.1
Planning
3.3.1.1 Coordinate meeting
3.3.1.2 Set agenda
3.3.2
Document
3.3.2.1 Discussion of requirements
3.3.2.2 Develop plan
3.3.2.3 Document plan
4.0 Monitoring and Controlling
4.1 Change requests
4.2 Documentation
5.0 Closing
5.1 Update project documentation 4
Solution details:
Answered
QUALITY
Approved
ANSWER RATING
This question was answered on: Sep 13, 2020
PRICE: $15
Solution~00021147653121.docx (25.37 KB)
This attachment is locked

Pay using PayPal (No PayPal account Required) or your credit card . All your purchases are securely protected by .
About this Question
STATUSAnswered
QUALITYApproved
DATE ANSWEREDSep 13, 2020
EXPERTTutor
ANSWER RATING
GET INSTANT HELP/h4>
We have top-notch tutors who can do your essay/homework for you at a reasonable cost and then you can simply use that essay as a template to build your own arguments.
You can also use these solutions:
- As a reference for in-depth understanding of the subject.
- As a source of ideas / reasoning for your own research (if properly referenced)
- For editing and paraphrasing (check your institution's definition of plagiarism and recommended paraphrase).
NEW ASSIGNMENT HELP?
Order New Solution. Quick Turnaround
Click on the button below in order to Order for a New, Original and High-Quality Essay Solutions. New orders are original solutions and precise to your writing instruction requirements. Place a New Order using the button below.
WE GUARANTEE, THAT YOUR PAPER WILL BE WRITTEN FROM SCRATCH AND WITHIN A DEADLINE.